Bridge Projects
Fulton Road Bridge, Cleveland, Ohio
Contractor: Kokosing Construction Company, Inc./Fru-Con Construction Corporation
Precast post-tensioned arch segments used in the replacement of the historic Fulton
Road Bridge. Project design utilizing three (3) arch segments forming one (1) complete
arch with four (4) arches per span, for a total of seventy-two (72) pieces. Pieces
weighed approximately 75 tons (150,000 lbs). Carr Concrete's transporation fleet
was responsible for delivery of the precast segments.
|
|